Purpose/Description:

  • This project’s intended result is to consolidate printing devices throughout the IMSA community into several strategically located black and white or color high speed, high efficiency multi-function printer/copier/scanner devices. This project was initiated by a joint directive from Central Management Services (CMS) and the Governor’s Office. The directive from CMS only addressed black and white devices, however this project will be also considering color printing needs for the Academy. If you would like to review the zone map developed for the consolidation plan please stop by the ITS Office. The schedule for deploying the new multi-function devices was based on the age of existing devices, issues with existing devices and potential cost savings, but is ultimately subject to ongoing budget constraints. Existing printers will be phased out or re-allocated depending on service and support availability, repair costs or institutional needs. 

Milestone Dates (subject to change):

  • Complete/Submit CMS “Current State” Evaluation Form: Completed
  • Review CMS Consolidation Plan: Completed
  • Submit IMSA Revisions to CMS Plan: Completed
  • Printer Consolidation Plan Approval: Completed
  • Deploy Xerox Multi-Function Device to A Wing Copy Center (Zone 16): Completed
  • Deploy Xerox Multi-Function Devices: Scheduled for FY14: Completed
  • Deploy Xerox Multi-Function Devices: Scheduled for FY15: Completed
  • Deploy Xerox Multi-Function Devices: Scheduled for FY16: Completed
  • Deploy Xerox Multi-Function Devices: Scheduled for FY17, Completed
  • Deploy Xerox Multi-Function Devices: Scheduled for FY18, In Process
    • Replace devices who's leases end in 2018
    • New Color Device in Administrative Copy Room – DONE
  • Deploy Xerox Multi-Function Devices: Scheduled for FY19, Pending Budget​​